Monday, July 26, 2010

7/26/0




Well, today was the day we were supposed to be done. 6 months ago we closed on the mansion. Were about 90% done at this point. Should be done in about 3 weeks.

New sheetrockers/painters started yesterday and got rest of master bath rocked/spackled.

Phil go kitchen mostly done and new windows in.

This week will see hopefully

1. Kitchen done, appliances in and trim up. Walls and trim painted.

2. Wood back up. Walls and ceiling painted.

3. Master bath primed, painted, trim up. Floors in.

All painting finished upon house.

Next week should be floor refinishing on one. Following week is any final elect and plumbing and inspections.


- Posted using BlogPress from my iPhone