Sunday, March 14, 2010

Update! 3/14/10

So we got home from vacation and boy did the house change!! While we were gone...

1. Mom painted the safe room
2. Roofers finished the main roof. Alot of repairs were done to the rafters and wood underneath. Apartment and porches are next.
3. Garage demoed 90% Last cleanup had to wait for bee guy to come get the huge hive out.
4. Right back porch room peeled inside to find glass windows floor to ceiling in good shape.
5. Collapsed staircase removed and original porch floor revealed to be in good shape
Floor in window room also has underlayer of wood floor condition to be determined
6. Removalof drop ceilings in 3rd fl utility and library.
7. Old doorway in first fl hall reopened for powder room
8. Kitchen gutted and now empty.
9. 2nd floor bath gutted and ready to go
10. 3rd floor utility room floor removed and ready for laminate

They've really done alot while we were gone. Especially with the continued rain issue

A ton of bushes were cleared but still more to go. Will wait on a chipper until everythings cut as they're pretty expensive to rent.

Will load pics later!!